After 170 Tonne of fill was removed
Friday, 31 January 2014
Site Cut
Yesterday we were suprised to find out off one of our lovely neighbours that there was an excavator on our site working! Our SS called us shortly after to let us know what was happening and what he expects to happen in the next week or so. We have a fair bit of extra fill that needs to be taken away (at our cost) as we have asked the excavator to cut as close as possible to the boundary around the block to save us time later on, and for the fact that getting a machine in later will be virtually impossible.
Tuesday, 28 January 2014
Ready To Go
After a long 7 months in admin, we are finally in the construction phase. We have been promised that our file will be finally handed over to our SS. Rawson have provided us with his name and number, now we just need to wait for him to make contact.
Here is a picture of what our block looks like at the moment - pre house construction.
Friday, 17 January 2014
Pegged!
We finally recevied our final construction plans on Wednesday 15th January, which was also the first day of our 30 week construction period. We also received a nice suprise, when one of our neighbours informed us that our block had been pegged. Our file is going to be handed over to our SS next week, so we are patiently waiting now for a call from him to let us know what will be happening and when.
Thursday, 9 January 2014
Final Plans - Still Waiting
Next wednesday marks the first day of our 30 week construction period. Unfortunately, we wont be seeing anything on site for a few weeks at least as we are still waiting for our final plans, which will hopefully be ready next week. Then our file will then be given to our SS, and then we should start seeing our home being built. Worst case senario we should have handover no later than 7th August 2014.