15th Jan 2014 1 Final plans received / Site Pegged
16th Jan 2014 1 Final plans signed and returned
17th Jan 2014 1
18th Jan 2014 Sat
19th Jan 2014 Sun
20th Jan 2014 1
21st Jan 2014 1
22nd Jan 2014 2
23rd Jan 2014 2
24th Jan 2014 2
25th Jan 2014 Sat
26th Jan 2014 Sun
27th Jan 2014 2
28th Jan 2014 2
29th Jan 2014 3 SS to receive file
30th Jan 2014 3 Site cut
31st Jan 2014 3 Site cut
1st Feb 2014 Sat
2nd Feb 2014 Sun
3rd Feb 2014 3
4th Feb 2014 3
5th Feb 2014 4 Layout marked up, string line
6th Feb 2014 4 Piering & Origin rang about elec & gas
7th Feb 2014 4
8th Feb 2014 Sat
9th Feb 2014 Sun
10th Feb 2014 4
11th Feb 2014 4 Plumbing, site fence erected & tap
12th Feb 2014 5
13th Feb 2014 5 Rawson signage erected on fence
14th Feb 2014 5 Port-a-loo & sediment control fence erected
15th Feb 2014 Sat
16th Feb 2014 Sun
17th Feb 2014 5 Formwork started - alfresco & right side
18th Feb 2014 5 Formwork continued, reo & waffle pods started
19th Feb 2014 6 Reo & waffle pods finished - still more formwork to be done
20th Feb 2014 6
21st Feb 2014 6 Engineer inspection, formwork finally finished
22nd Feb 2014 Sat
23rd Feb 2014 Sun
24th Feb 2014 6
25th Feb 2014 6 Slab
26th Feb 2014 7 Termimesh installed, frame delivered, frame part erected
27th Feb 2014 7 Roof Trusses delivered
28th Feb 2014 7 RAIN DAY First progress payment received
1st March 2014 Sat
2nd March 2014 Sun
3rd March 2014 7 Wall framing completed , roof trusses started
4th March 2014 7 Roof trusses completed
5th March 2014 8 Windows installed & electricans on site. Gutters & fascia delivered
6th March 2014 8 Scaffold erected to front of house
7th March 2014 8 Gutters & fascia installed, roof tiles delivered, window protection applied
8th March 2014 Sat
9th March 2014 Sun
10th March 2014 8 Second progress payment received
11th March 2014 8 Scaffold erected around the rest of the house - ready for tiling
12th March 2014 9 Roof tiling started
13th March 2014 9
14th March 2014 9 Site clean of excess dirt from piering
15th March 2014 Sat
16th March 2014 Sun
17th March 2014 9 Walk -thru with SS, Bricks delivered
18th March 2014 9 Skip bin emptied
19th March 2014 10
20th March 2014 10 More Roofing done - still not finished
21st March 2014 10
22nd March 2014 Sat Bricking started - 18 rows high on 3rd garage wall
23rd March 2014 Sun
24th March 2014 10 Bricks - back garage wall, front bedrooms started
25th March 2014 10 Bricks - front columns, right hand side of house started
26th March 2014 11 Bricks - front of house mostly finished, back started, right hand side continued
27th March 2014 11 RAIN DAY Bricks - around front windows started, 1/2 main bathroom done
alfresco columns started, stacker doors installed, more bricks delivered
28th March 2014 11 RAIN DAY Internal bricking to 3rd garage wall, ensuite & main bedroom
29th March 2014 Sat
30th March 2014 Sun
31st March 2014 11 3rd progess claim for brick received - still not finished!!! More bricking
1st April 2014 11 Roof finished, plumbing rough in completed, bricking continued, materials for eaves delivered
2nd April 2014 12
3rd April 2014 12 External taps installed, bathroom cavity slider frame delivered
4th April 2014 12 Eletrical rough in started. Meter box and backing plate installed
5th April 2014 Sat
6th April 2014 Sun
7th April 2014 12 Electrical rough in continued, installation of eaves started
8th April 2014 12 electrical rough in completed, eaves continued, timber feature started, downpipes started to be installed
9th April 2014 13 Installation on eaves continued
10th April 2014 13 Internal framework finally continued, waterproofing started
11th April 2014 13 Internal framework & air con rough in completed
12th April 2014 Sat
13th April 2014 Sun
14th April 2014 13 New windows delivered
15th April 2014 13 New windows installed, bath partially boarded up
16th April 2014 14 Insulation delivered, another window delivered
17th April 2014 14 Window installed, frame inspection, 2nd walk thru
18th April 2014 14 Public Holiday
19th April 2014 Sat
20th April 2014 Sun
21st April 2014 14 Public Holiday
22nd April 2014 14 Insulation 3/4 installed
23rd April 2014 15 Brickies returned, gyprock delivered
24th April 2014 15 Bricking continued
25th April 2014 15 Public Holiday
26th April 2014 Sat Gyprocking started
27th April 2014 Sun
28th April 2014 15 Bricking finally finished! Gyprocking continued
29th April 2014 15 Gyprocking continued - setting started
30th April 2014 16 Internal doors, skirting, arcitraves and door jams delivered
1st May 2014 16 Plastering continued, front door hung, internal fit out started
2nd May 2014 16 2 skip bins delivered, site cleaned up, plaster continued
3rd May 2014 Sat Plastering continued
4th May 2014 Sun Plastering continued
5th May 2014 16 Internal fix out started
6th May 2014 16 Internal fix out continued, bricks cleaned
7th May 2014 17 Internal fix out continued
8th May 2014 17 3rd walk thru, fix out continued, 2nd stage waterproofing done
9th May 2014 17 4th progress claim for internal linings received Internal fix out continued
10th May 2014 Sat
11th May 2014 Sun Painting started
12th May 2014 17 water tank delivered, renderers started, internal fix out continued
13th May 2014 17 Water tank connected, internal fix out continued
14th May 2014 18 Glass in front window, blinds ordered, render, eaves completed etc
15th May 2014 18 Gravel/all weather access driveway pad laid
16th May 2014 18 Electrican onsite to work on meter box and cut out holes for power points etc
17th May 2014 Sat
18th May 2014 Sun
19th May 2014 18 Air con vent holes cut out in ceilings
20th May 2014 18
21st May 2014 19 Internal painting continued
22nd May 2014 19 painting continued, garage doors installed
23rd May 2014 19 Internal painting continued
24th May 2014 Sat External painting done (render painted the wrong colour)
25th May 2014 Sun
26th May 2014 19
27th May 2014 19 Tiler has prepped floor ready to for floor tiles to be laid
28th May 2014 20 Floor tiles laid in main bathroom, ensuite and toilets
29th May 2014 20 Floor tiles laid in laundry, kitchen delivered
30th May 2014 20 vanities & laundry installed, wall tiles started in main bathroom
31st May 2014 Sat
1st June 2014 Sun
2nd June 2014 20 Kitchen, butler pantry & hallway cabinetry installed, tiling continued
3rd June 2014 20
4th June 2014 21 Tiling continued
5th June 2014 21 Tiles grouted
6th June 2014 21 5th progress claim for fix out received
7th June 2014 Sat
8th June 2014 Sun
9th June 2014 21 Public Holiday
10th June 2014 21 4th walk thru painters back
11th June 2014 22 Painting continued
12th June 2014 22 Benchtops installed
13th June 2014 22 Air conditioner, vents and panel installed
14th June 2014 Sat
15th June 2014 Sun
16th June 2014 22 Tiler back to finish bathroom splashbacks, appliances installed
17th June 2014 22 Mirrors installed, screen in ensuite installed, plumbing fit out completed, gas system installed, water tank hooked up, electrical fix out started, down pipe connected
18th June 2014 23
19th June 2014 23 Skirtings in bedrooms installed, door handles and door stops intalled, main bathroom shower screen installed, front door handle installed
20th June 2014 23
21st June 2014 Sat Timber flooring installed
22nd June 2014 Sun
23rd June 2014 23 Skirtings installed, blueboard installed above front bedroom window
24th June 2014 23 Painters back to complete paintworks internal and external
25th June 2014 24 Carpet installed, windows cleaned
26th June 2014 24
27th June 2014 24 Independant inspection booked for 7am PCI @2pm
28th June 2014 Sat
29th June 2014 Sun
30th June 2014 24 Final Invoice received
1st July 2014 24 Occupation certificate paperwork completed and sent back
2nd July 2014 25 Carpenter back, portico redone, front door fixed, floors cleaned
3rd July 2014 25 Handles, hooks etc installed, weep hole covers removed, section
above front window pulled down
4th July 2014 25 Tiler back to fix up tile issues
5th July 2014 Sat
6th July 2014 Sun Plasterers back fixing up internal plaster work
7th July 2014 25 Carpenter back to blueboard above front window
8th July 2014 25 External site clean
9th July 2014 26
10th July 2014 26 HANDOVER @ 8am - painters back to finish internal painting, and some external painting, electrician in to fix gas cook top, fly screens installed
11th July 2014 Our electrian in to install our downlights etc, excavator onsite to dig out footings for retaining walls
12th July 2014 Sat Dig out more footings for retaining walls, move stuff into house from storage
13th July 2014 Sun Hang up blinds - unpack boxes
14th July 2014 Pour footings for retaining walls, form up driveway
15th July 2014 Pour double driveway
16th July 2014 Pour third driveway, start retaining walls - Rawson renderer is a no show
17th July 2014 Continue with retaining walls
18th July 2014 Continue with retaining walls - Rawsons cleaners finally show up, splashback also finally installed
19th July 2014 Sat Start to reinstall side fence
20th July 2014 Sun Fix faulty lights in bedrooms
21st July 2014 Core fill retaining walls
22nd July 2014 Finish erecting side fence, agi line put in behind walls, driveways sealed
27th July 2014 Sun Stripped pool covers off
28th July 2014 Stegbar came to fix rubber in bathroom window, and scratch on stacker door.
30th July 2014 Beacon lighting electrician out to replace faulty light. Winning appliances delivered new dishwasher
1st August 2014 Plumber returned to install replacement dishwasher, renderer finally showed up to start fixing the overhanging frame in the garage
4th August 2014 Renderers returned to finish work in the garage
7th August 2014 Back filled behind retaining walls
8th August 2014 Side path formed up, footings dug out for front left retaining wall
9th August 2014 Sat Side path poured, footings poured
10th August 2014 Sun Front garden area leveled off, and turf laid
11th August 2014 Front left retaining wall erected, caps intstalled on retaining wall
12th August 2014 Front retaining wall core filled, caps installed on remaining retaining walls
14th August 2014 Coping pavers around pool started to be installed
15th August 2014 Coping pavers finished
26th August 2014 Pool surround & alfresco formed up, outdoor shower installed
27th August 2014 Pool surround & alfresco poured
28th August 2014 Rawson tiler returned to tile under the bath hob
29th August 2014 Slab/path for garbage bins poured, capping on retaining walls finished
30th August 2014 Pool surround and path acid washed
1st September 2014 SS & Plasterer came to inspect defects in plaster
2nd September 2014 Grouting of coping pavers completed, front path poured
5th September 2014 Alfresco concrete polishing started Rawson plasterer mark up faulty work to be fixed
6th September 2014 Concrete polishing continued
8th September 2014 Electrican hooked up power points in pool area and front sensor lights
9th September 2014 Concrete polishing completed
12th September 2014 Glass pool fence installed
17th September 2014 Renderer to render front retaining walls
18th September 2014 Pool gate installed Rawson plasterers returned to fix defects
19th September 2014 Underlay finished
20th September 2014 Turf laid, pool filters etc connected
22nd September 2014 Rawson plasterer returned, glass pool fencing completed
23rd September 2014 Rawson plasterer finished
24th September 2014 Rawson painters returned
1st October 2014 Rawson painter returned again to redo paint work, and remove paint from carpet and furniture
19th October 2014 Front retaining walls painted
22nd October 2014 Maintenance list sent to rawson (9 pages long with pictures)
No comments:
Post a Comment