3rd May 2013 Offer made and accepted on land
23rd May 2013 Paid $950 deposit to Rawson Homes for tender
28th May 2013 Contracts on land exchanged
23rd June 2013 Tender presentation
24th June 2013 0 Signed tender & paid $3000 deposit
25th June 2013 1 Land settled, Advised colour pack sent, CSO will ring this week
26th June 2013 2 Colour pack received
27th June 2013 3
28th June 2013 4 Our CSO contacted us
29th June 2013 5
30th June 2013 6
1st July 2013 7
2nd July 2013 8
3rd July 2013 9
4th July 2013 10
5th July 2013 11
6th July 2013 12
7th July 2013 13
8th July 2013 14 CSO emailed,advised we dont require landscape plans for estate
9th July 2013 15
10th July 2013 16
11th July 2013 17
12th July 2013 18
13th July 2013 19
14th July 2013 20
15th July 2013 21
16th July 2013 22 Trees on block chopped down
17th July 2013 23
18th July 2013 24 Pre-approval from bank received
19th July 2013 25
20th July 2013 26
21st July 2013 27
22nd July 2013 28 Advised by CSO that we should receive our plans early next week
23rd July 2013 29
24th July 2013 30
25th July 2013 31
26th July 2013 32 Received our 1st set of plans via email
27th July 2013 33
28th July 2013 34
29th July 2013 35
30th July 2013 36
31st July 2013 37
1st August 2013 38
2nd August 2013 39 Signed off on shed/bedroom wall variation and emailed to CSO
3rd August 2013 40
4th August 2013 41
5th August 2013 42
6th August 2013 43 Appointment @ 11am to go over plans and make changes
7th August 2013 44 Changes faxed off to Head Office
8th August 2013 45 Finally received hard copies of 1st set of plans in mail
9th August 2013 46
10th August 2013 47
11th August 2013 48
12th August 2013 49
13th August 2013 50
14th August 2013 51
15th August 2013 52
16th August 2013 53 Received Check Plan Variations via email
17th August 2013 54 Deposit for pool paid
18th August 2013 55
19th August 2013 56 Emailed CSO back with changes to be made to variations
20th August 2013 57
21st August 2013 58 CSO rang to advise that house is too big for block of land. With driveways and pool we are over by 42sqm
22nd August 2013 59 Went to chisholm to look at 2 storey house options
23rd August 2013 60 1/2 way mark for pre-build process!!!
24th August 2013 61 Meeting at Chisholm to discuss house options
25th August 2013 62
26th August 2013 63 Went to council with plans, advised ok to proceed with house
Updated check plan variations received, signed off on and returned via email.
27th August 2013 64 Advised that it will be about 20 working days until our DA quality plans are ready
28th August 2013 65
29th August 2013 66
30th August 2013 67
31st August 2013 68
1st September 2013 69
2nd September 2013 70 External colours submitted
3rd September 2013 71
4th September 2013 72
5th September 2013 73
6th September 2013 74
7th September 2013 75
8th September 2013 76
9th September 2013 77 DA plans received - variation to driveway required
10th September 2013 78 Variation received and sent back. Back to drafting for amendment. Revised DA plans received, signed and sent back $7000 deposit paid.
11th September 2013 79
12th September 2013 80
13th September 2013 81
14th September 2013 82
15th September 2013 83
16th September 2013 84
17th September 2013 85
18th September 2013 86 Hunterwater wont endorse plans - tank to close to sewer
19th September 2013 87 Engineering plans now required to show tank wont interfere with sewer. 2 weeks and they will be completed.
20th September 2013 88
21st September 2013 89
22nd September 2013 90
23rd September 2013 91
24th September 2013 92 Finally recieved and email to make colour appointment
25th September 2013 93 Rang Tile Direct and YHC to arrange appointments
26th September 2013 94
27th September 2013 95
28th September 2013 96
29th September 2013 97
30th September 2013 98
1st October 2013 99 Engineer plans received - ready for hunter water to approve
2nd October 2013 100
3rd October 2013 101
4th October 2013 102 Hunter Water stamped plans. Plans lodged with Mine Subsidance
5th October 2013 103
6th October 2013 104
7th October 2013 105
8th October 2013 106
9th October 2013 107
10th October 2013 108 Mine subsidance stamped and sent plans back to Rawson
11th October 2013 109
12th October 2013 110
13th October 2013 111
14th October 2013 112
15th October 2013 113
16th October 2013 114 Plans from Mine Subsidance finally recevied. Plans express posted to council for DA approval
17th October 2013 115 LMCC should receive plans in mail. DA number recevied for pool.
18th October 2013 116 DA number allocated for house plans.
19th October 2013 117 Accent Carpets @ 10 am & Colour selections @ 1pm
20th October 2013 118
21st October 2013 119 Tile Direct @ 7:30am & YHC for electrical appointment @ 11am
22nd October 2013 120 Questioned Bal rating with rawson, down as bal 29.
23rd October 2013 121
24th October 2013 122 Sourced second opinion on bal rating and advised it should be lower
25th October 2013 123 Rawson said we could get another bushfire report completed
26th October 2013 124
27th October 2013 125
28th October 2013 126 New bushfire assessment completed and sent to council.Now bal 12.5
29th October 2013 127
30th October 2013 128 Received variation credit for bushfire rating reduction & variation for electrical
31st October 2013 129
1st November 2013 130 DA approval for house and pool received
2nd November 2013 131
3rd November 2013 132
4th November 2013 133
5th November 2013 134 New CSO assigned! Contract arrived in mail
6th November 2013 135
7th November 2013 136 Contract & CC form express posted back to Rawson
8th November 2013 137
9th November 2013 138
10th November 2013 140
11th November 2013 141 Bank received contract for loan - CC paperwork lodged
12th Novembe 2013 142
13th November 2013 143 CC issued - only took 2 days!!!
14th November 2013 144 Should finally receive colour selection variations - still waiting for 1/2 of them
15th November 2013 145
16th November 2013 146
17th November 2013 147
18th November 2013 148
19th November 2013 149
20th November 2013 150
21st November 2013 151 Pool getting installed, Home Loan approved
22nd November 2013 152 Pool installation completed. Received our colour selections prices
23rd November 2013 153
24th November 2013 154
25th November 2013 155 Signed off on colour variations - file off to drafting and estimating
26th November 2013 156
27th November 2013 157
28th November 2013 158
29th November 2013 159
30th November 2013 160
1st December 2013 161
2nd December 2013 162
3rd December 2013 163
4th December 2013 164 Rawson finally have all paperwork require for countdown to start
5th December 2013 165 Final Plans received - changes to window height from FFL needed
6th December 2013 166 Variation for window heights signed - plans need to be re-done :(
7th December 2013 167
8th December 2013 168
9th December 2013 169 Received drawings of kitchen, laundry, pantry and bathrooms
10th December 2013 170
11th December 2013 171
12th December 2013 172
13th December 2013 173
14th December 2013 174
15th December 2013 175
16th December 2013 176
17th December 2013 178
18th December 2013 179
19th December 2013 180
20th December 2013 181 Rawson close down for xmas
6th January 2014 182
7th January 2014 183 Advised by CSO that plans wont be finished until mid Jan :(
8th January 2014 184
9th January 2014 185
10th January 2014 186
11th January 2014 187
12th January 2014 188
13th January 2014 189
14th January 2014 190
15th January 2014 191 Final plans received - Construction period to commence