Monday, 25 November 2013
Final Bank Approval Received
On Thursday we were also advised that our loan have been fully approved. We have signed all the paperwork and are now just waiting for the bank to issue the Authority to Commence Construction Letter so we can forward it on to rawson. We are almost there!!
We Have A Pool
On thursday our pool started to get installed, and it was completed on friday. We got a Billabong plunge pool, as we dont have alot of room, but its going to be perfect for us. Cant wait until summer 14/15 to have a dip.
Block before the pool is installed
Markings of where pool will be placed
All the fill that was removed
The shell
Before it has been backfilled and water put in
All done - until the house is finished
Monday, 18 November 2013
Construction Certificate Issued
Our paperwork for our construction certficate was sent to certifiers on 11/11/13 and to our suprise we we advised today that it has been issued and it is dated 13/11/13. We are now just waiting for our bank approval to come through, once that happens the 20 working day count down till construction starts is on!!
We are still waiting for a few colour prices to come through - its been over a month since our appointment - hopefully they are sorted this week so they is no delays in getting our final plans and orders in.
We are still waiting for a few colour prices to come through - its been over a month since our appointment - hopefully they are sorted this week so they is no delays in getting our final plans and orders in.
Friday, 1 November 2013
Council Approval Received
So today marks day 130 of our admin period..... and today we received DA approval. I can finally see the light at the end of the tunnel. We are now hopeing to have contract and construction certificate paperwork completed by the end of next week and then patiently wait for final bank approval and site start.